Updated Notice of Construction

Notice of Construction: High Street Sanitary Sewer Lining

Due to weather delays, the sanitary sewer lining work (noted in the March 28th notice) will now begin on April 9th and is expected to finish by April 17th.

The order of work will be:

  • April 9th and 10th
    • 233 High Street to the east side of the Albert Street intersection.
    • Sanitary services will not be available between 9:00 PM on the 9th and 11:30 AM on the 10th.
  • April 10th and 11th
    • 173 High Street to the west side of the Albert Street intersection.
    • Sanitary services will not be available between 9:00 PM on the 10th and 11:30 AM on the 11th
  • April 14th – 17th
    • Installation of sewer service liners (“tophats”) from 173 to 233 High Street.
    • No disruption of sanitary services.

Crews will be working from 8:00 PM until 1:00 PM the next day.

For questions about the above scheduled work please, contact the Town’s Engineering Services at engineering@saugeenshores.ca.

We appreciate your cooperation. Thank you!